Optimism bias
The habit of underestimating cost and time and overestimating benefit, and how to allow for it.
What it is for
Optimism bias is the tendency for people planning something to expect it to cost less, take less time and deliver more than it later does. The Treasury’s Green Book asks for an explicit adjustment: take the first estimate and add an uplift based on what similar work has cost in the past, then reduce it only where you can show you have dealt with the causes. Whatever the formal method, the idea travels well. Compare your plan with what happened last time, not with what you hope will happen this time.
How it works
- Make your best first estimate of cost, time and benefit.
- Find evidence of how similar work performed, from your own organisation if you can or from published examples.
- Add an allowance for the usual overrun, and cut the claimed benefit by what such work usually delivers.
- Reduce the allowance only for specific risks you have already removed, and write down which ones.
- Show the adjusted figure next to the first estimate so approvers can see both.
- Track the actuals and feed them back into the next estimate.
When not to use it
It is a correction for judgement, not a contingency to be spent. Do not pad every estimate by the same percentage without looking at the work, and do not apply it on top of a contingency that already covers the same risk. It also does not replace a good plan. It tells you a figure is risky, not how to make it less so.
Often used with