RAID log

One list for risks, assumptions, issues and dependencies, kept alive for the life of the work.

What it is for

A RAID log keeps four kinds of thing in one place. Risks may happen. Assumptions are things you are treating as true without proof. Issues are problems that have already happened. Dependencies are things you need from someone else, or that someone else needs from you. Its value comes from the owner and the date against each line, because an item without an owner is just worry written down. It is also a good way to spot an assumption turning into an issue before it costs you.

RRiskMight happene.g. The supplier may miss the dateAAssumptionTreated as true, not yet provene.g. Staff will be free in MarchIIssueHas already happenede.g. The test system is downDDependencyNeeds something from someonee.g. The network upgrade finishes firstEvery line gets one owner and a date to look at it again.
Keep all four in one log, so an assumption that fails becomes an issue you can see coming.

How it works

  1. Create four sections, one for each type.
  2. Add each item in plain words, with what it affects.
  3. Give every item one named owner and a date to look at it again.
  4. Score risks and issues the same way so they can be compared, for example with a risk matrix.
  5. Review the log regularly: close items, escalate the ones nobody on the team can fix, and move risks to issues when they land.
  6. Keep closed items for a while so you can see what you learned.

When not to use it

A log that is only updated before a steering group is a record, not a tool. If it has hundreds of lines, nobody reads it, so tidy it, merge duplicates and close the dead ones. It is not a substitute for talking to the people doing the work.