Work breakdown structure
Breaking the whole job into pieces small enough to estimate, own and track.
What it is for
A work breakdown structure lists everything a piece of work has to produce, split level by level until each piece is small enough for one person or team to own and to estimate. It describes the deliverables, not the activities, so it shows what the job is before anyone argues about how long it will take. It is the base for plans, budgets and risk lists, and it is the quickest way to find the work nobody has thought about.
How it works
- Write the end result at the top as a single statement.
- Split it into three to six main deliverables, with no overlaps.
- Split each again until a piece can be estimated and given to one owner.
- Check that the lower levels add up to the level above, with nothing missing and nothing counted twice.
- Give each piece an owner and a reference, so the plan, budget and risk log can point to it.
- Keep it up to date when scope changes.
When not to use it
It shows what is in scope, not the order or timing of the work, so it is not a plan by itself. Add dependencies and dates once it is stable. Do not go deeper than people can manage. A thousand tiny boxes are harder to keep up to date than a hundred sensible ones.